Create Resource Plan in Project Server 2013

What is Resource Plan in Project Server ?:-

What is a Resource Plan? In Project Server, a Resource Plan in Project Server offers a way to estimate resources requirements at a high level without having a detailed schedule. For any project, you can specify the estimated effort required by resources using either Generic Roles or named people. Typically, Generic Roles would be used at this stage of the project. It’s important to note that the Resource Plan will not impact the project schedule in any way, shape or form. Resources listed in the Resource Plan will not even automatically show up on the schedule. They are completely separate.

Step 1: Go to PWA home page.

Resource Plan in Project Server

Step 2: Open project center to click on projects.

Step 3: Now build a Resource Plan for a particular project

Step 4: Now select a particular project automatically projects ribbon tab will be open.

Resource Plan in Project Server

Step4: In projects ribbon click on Resource Plan, you will see a blank screen

Resource Plan in Project Server

Step 5: In Plan ribbon tab you can calculate resource utilization from the Project Plan dropdown

Step 6: In Plan ribbon tab go to build the team, 2013 .there is all the resource listed that you can access.If there are no resources then you have to add resources in PWA site.How to add resources in PWA site go to my post to click here. Active Directory Resource Pool synchronization in Project Server 2013 

Step 6: Select resources you want to assign to a particular project, and click Add.

Resource Plan in Project Server Resource Plan in Project Server

 

 

Step 7: In team ribbon tab click to save and close button.It will redirect to plan ribbon tab and all selected resources will appear.[AdSense-A]

Resource Plan in Project Server

 

Step 8: Your resource plan created. You can check also Resource Availability to checked checkbox of  Resource Name. And click on Resource Availability in Team

Resource Plan in Project Server

Step 9: Availability ribbon tab will be open. Here you can check every resource availability by date.

Resource Plan in Project Server Resource Plan in Project Server